Project Spotlight
Power Station, Ravenswood QLD
The Gold Mine Required NPE to start and run a 12 MW ball mill, the diesel power station was required to go from no load to 18MW starting current and then back to 12MW continuous load as the mill gets to rated speed. NPE designed a 26 MW power station complete with 12MW of resistive…
Read MoreScreening Solution, Sewage Treatment Plant – Byron Bay NSW
NPE was asked to provide a screening solution that would allow the local council to take their entire inlet works offline for an extended period to facilitate the strip out, re-coating and refurbishment of their inlet works at the Byron Bay sewage treatment plant. The solution required the sewage treatment plant to be operational 24/7…
Read MoreSpear Dewatering for Deep Sewer Installation
Georgiou contacted NPE to install a Dewatering system into a new subdivision in Ellenbrook, WA. This project required 1km of spear Dewatering for deep sewer. Our Dewatering & Water Treatment team provided our client with Piston Pumps, BBA100 Pumps, a Clarifier, and CDU Unit. This was able to keep the site dry & the water…
Read MoreNorthern Dive Update – WA
Our client Tonkin Gap Alliance is constructing the Northern Dive as part of its METRONET Morley-Ellenbrook Line rail enabling works. The Northern Dive requires dewatering of over 900,000kL during its construction. This required NPE to design the dewatering set-up to allow for the extraction water’s treatment and re-infiltration to protect the adjacent Banksia Woodland threatened…
Read MorePipelines & Construction – Ceduna SA
The Jacinth-Ambrosia mine site is located approximately 300km northwest of Ceduna, South Australia.An existing Mining Unit Plant is to be relocated from Jacinth North to the Ambrosia deposit, approximately 5km away, whilst returning the ModCoD tailing deposition to Jacinth North. The Project is being managed and resourced from WA with logistic and administration support from…
Read MoreSewage Bypass, 18m Deep Manhole – Victoria
NPE were engaged in managing and constructing a sewer bypass for new sewer connections works to be carried out in a 10-day operation. Our Melbourne team are the leading provider in bypass pumping. We deliver the complete bypass solution. With flow management plans, Telemetry displays full visibility on critical pumping performance values & flow, pumping…
Read MoreMurray River Flooding – SA
Due to the recent Murray River flooding, NPE were engaged by the client to provide a proposal for contingency Bypass Pumping for the MBO1 Pumping Station which draws water directly from the Murray River and via processing and several booster pump stations eventually feeds water to the southern suburbs of Adelaide. Once the proposal was…
Read MoreQuarry Dewatering – WA
The client contacted NPE for a High Head Water Pump capable of pumping water to an RL increase of approx. 60m to assist in the dewatering of a quarry in WA. NPE offered a pump package that helped drain the pit on schedule and within budget.
Read MoreBypass Critical Works – Victoria
Bypassing a critical sewer pump station for major upgrades! Swan Street sewer pump station is the most crucial station in Wangaratta’s sewer network as it gathers and transports almost half of the town’s waste to the treatment facility. The station, which is over 70 years old, has recently undergone renovations to accommodate the town’s expanding…
Read More