NPE were engaged by Alita Constructions to install dewatering at 2 different locations at their project located on Dowd St, Welshpool.
The purpose of the install was to allow the client to excavate below the water table to complete the final connection of the site stormwater system and install a large aerobic treatment unit.
We had our dewatering pumps and equipment delivered to site, the systems installed and running within 48 hours! The job ran for most of the week.
The client was really happy and the job was completed safely, and in a timely manner.
RECENT POSTS
Dewatering for the construction of an apartment complex in Sydney, NSW
NPE maintains a large and diversified range of high-end pumping, power generation and associated equipment…
Read MorePerth City Link Rail
NPE was contracted with the Perth City Link Rail Alliance to provide a detailed design,…
Read MoreRoy Hill Iron Ore Train Unloader
The Roy Hill project includes the construction of a new iron ore mine at Roy…
Read MoreDewatering & Water Treatment at Perth Busport Project, WA
NPE were involved in this project for the drilling and installation of a series of…
Read MoreElizabeth Quay Project, WA
The Elizabeth Quay project is located in the centre of Perth’s river foreshore and located…
Read More