Wellpoint Dewatering – WA

NPE were engaged by our client regarding installing an LLDPE 11000 litre tank.

The depth to the static groundwater level was 1.5m below surface ground level, and the concrete footing for their tank base needed to be dry down to 2.6m invert from GL (ground level).

NPE mobilised to the site and installed a Wellpoint dewatering system by hand jetting method with appropriate spacing around the 12m x 5m perimeter to the required pre-determined depth, as this was the most suitable and efficient method of temporarily lowering the water table for this excavation.

The dewatering effluent was discharged into the allocated onsite infiltration basin for this 8-day duration.

This is the 2nd dewatering system in 4 months that NPE have installed for our client’s new Water Treatment facility in Osbourne Park, Perth, WA.

Both jobs were a dry success.

RECENT POSTS

Dewatering for the construction of an apartment complex in Sydney, NSW

NPE maintains a large and diversified range of high-end pumping, power generation and associated equipment…

Read More

Perth City Link Rail

NPE was contracted with the Perth City Link Rail Alliance to provide a detailed design,…

Read More

Roy Hill Iron Ore Train Unloader

The Roy Hill project includes the construction of a new iron ore mine at Roy…

Read More

Dewatering & Water Treatment at Perth Busport Project, WA

NPE were involved in this project for the drilling and installation of a series of…

Read More

Elizabeth Quay Project, WA

The Elizabeth Quay project is located in the centre of Perth’s river foreshore and located…

Read More